The apartment is delayed and the developer has collapsed: the Supreme Court on compensation when the lender completes construction

Apartment keys and unmarked documents beside a set of scales, with an illustrated residential building in the background
Illustration: purchase contracts, keys and the legal balance in a residential project.

A party that financed a construction project and chose to complete it through a receiver cannot rely on purchase contracts to collect the remaining price while rejecting the obligations attached to them. In a judgment dated 7 October 2026, the Supreme Court clarified how this principle applies to compensation for delayed apartment handover.

The decision concerned an appeal by apartment buyers in a project at 63 HaNevi'im Street in Bat Yam. It is not an order to transfer a fixed sum immediately to every buyer in a failed project: the court returned the case to the lower court to examine entitlement and calculate any award. The practical development concerns how the debt should be examined and its status within the receivership proceedings.

Completing the project does not erase the contract

The dispute reached the Supreme Court after completion of construction was chosen as the course of action in proceedings following the project's failure. The buyers sought consideration of compensation for the delay, not just the outstanding money demanded from them to receive the apartment.

The judgment concerning the Bat Yam project distinguishes between choosing to fulfill the obligation to deliver apartments and other ways of realizing security. When the sale agreements continue to govern the work, it is not possible to select only the clauses that serve completion of the project and treat obligations to buyers as though they have disappeared.

Justice Ruth Ronnen wrote the principal opinion. Deputy President Noam Sohlberg and Justice Yael Willner agreed to allow the appeal, with observations on a separate issue concerning agreements and waivers. Their shared conclusion concerned the duty to examine buyers' rights within the framework under which the lender had chosen to continue the project.

For a buyer, this changes the starting point of the discussion: saying that the original company encountered financial difficulties does not end the inquiry. It is necessary to examine who is completing construction, under which arrangement, which contracts were retained and the status of the obligations within the approved proceedings.

The receiver's appointment date may change the debt's status

One central distinction in the judgment is between compensation relating to the period before the receiver's appointment and compensation relating to the period afterward. This does not remove the question of entitlement to compensation; it also concerns where the debt stands relative to other payments.

Under the ruling, the component relating to the period after appointment may be an expense of the proceedings when the project continues under receivership. That status matters to payment priority, particularly in relation to debt secured by a floating charge. It does not establish that every debt owed to a buyer always takes precedence over every security interest or other creditor.

By contrast, compensation relating to an earlier period is examined as pre‑existing debt. The same handover delay may therefore span periods receiving different legal treatment. That is why the receiver's appointment date is more than a technical detail in a long document: it is information worth locating when preparing a claim or payment demand.

There is a difference between how much money is owed and which funds can pay it, in what order. Even a buyer with a strong compensation claim needs to examine both. The judgment sharpens this distinction instead of turning the entire waiting period into one sum with a uniform status.

What the Supreme Court did not award the buyers

The opinion concluded that the case should return to the district court to examine entitlement to compensation and the calculation. It also held that the priority of the component relating to obligations arising after the receiver's appointment must be considered. The Supreme Court did not replace that inquiry with a final compensation award for the delay.

The judgment therefore offers no formula into which only the number of months of delay can be entered to determine what will reach a bank account. The sale agreement, the law applying to it, handover dates and the parties' arguments must be examined. Even a superficially similar claim may raise different questions because of the project's documents and the course of the proceedings.

Nor does the ruling turn every bank or financing body into a general insurer against every delay. The analysis is tied to the route chosen to complete the project and the obligations retained within it. Presenting the outcome as a blanket promise of payment from any lender skips a central condition of the judgment.

Documents to gather before making an approach

A buyer in a similar position should start with the sale contract and its appendices, particularly the handover and payment provisions. Alongside these, gather delay notices, documents concerning the receiver's appointment, demands for payment of the balance and evidence of expenses incurred during the wait. These are starting points for an individual assessment, not a finding that every expense qualifies for reimbursement.

Build a single timeline: the contractual handover date, changes communicated, the start of proceedings and appointment of the officeholder, and the actual handover date if it has occurred. This makes it easier to identify which part of the claim concerns the earlier period and which concerns completion of construction.

The ruling should not be taken to mean that a buyer can independently offset an estimated sum against any payment demand or stop paying without examining the implications. Such action depends on the rights, documents and decisions in the case. Before offsetting a sum or signing a waiver, obtain legal advice addressing the particular project.

Receiving the keys without giving up the inquiry

The judgment's practical message is that completing construction and examining compensation are not mutually exclusive questions. Buyers can want the project finished while insisting that obligations to them be examined within the appropriate legal framework.

The Supreme Court did not complete the buyers' path to a final sum, but it clarified that choosing to continue the transaction requires attention to the side that protects them too. For someone waiting for an apartment in a project under receivership, the first question is now not only when the keys will arrive, but which obligations came with the decision to complete the building.

All articles

More on the site

Display and accessibility

Text size: 100%

Your choices are saved on this device only. For more details, see the Accessibility Statement.

Have a story for us?

An article idea, correction or question about the site? You can message us on WhatsApp and we will get back to you.